• The payment would likely be made to Sui Northern Gas Pipelines Limited (SNGPL) in next few days and after that it would start work on the provision of sui-gas in the leftover areas of sector I-14, said a press release issued on Friday.
  • Moreover, 29,250 meter long pipe line of two inches diameter and 501,110 meter long 1.25 inches diameter gas pipe line would also be laid in addition to up-gradation of existing sui-gas network and infrastructure in the sector.

ISLAMABAD: Capital Development Authority (CDA) has approved Rs 210.552 million for installation and provision of gas network in residual areas of sector I-14.

The payment would likely be made to Sui Northern Gas Pipelines Limited (SNGPL) in next few days and after that it would start work on the provision of sui-gas in the leftover areas of sector I-14, said a press release issued on Friday.

Under the project, SNGPL would lay 3470 meters long gas pipe of four inches diameter and will further establish door to door gas network in the area.

Moreover, 29,250 meter long pipe line of two inches diameter and 501,110 meter long 1.25 inches diameter gas pipe line would also be laid in addition to up-gradation of existing sui-gas network and infrastructure in the sector.

Provision of sui-gas in sector I-14 was longstanding demand of residents of the sector as the matter was pending since 1989.